Two fire incidents reported in Delhi, none injured
Fire officials confirmed that no injuries were reported in both incidents.
During the inspection, Shekhawat directed to expedite the STP works in Delhi, keeping in mind the December 2022 timeline.
After December 2022, there will be a difference in the quality of water in the river Yamuna in Delhi, said Union Minister for Jal Shakti, Gajendra Singh Shekhawat while inspecting the 564 MLD Okhla Sewerage Treatment Plant which is currently being constructed under the Yamuna Action plan-III.
During the inspection, Shekhawat directed to expedite the STP works in Delhi, keeping in mind the December 2022 timeline.
The Union Minister first visited the Chhat Ghat at ITO and took a boat from there to reach Okhla Boat Club, 12 kilometres away. From there, Shekhawat reached the Okhla STP site by road.
Advertisement
As per the cost-sharing arrangement, 85% of the cost is borne by the central government under the Namami Gange Programme and 15% by the state government.
The total sanction cost of the Okhla STP project is Rs. 665.78 crore.
Okhla STP is the biggest sewage treatment plant in Asia. After the construction of this 564 MLD, there will be a considerable improvement in the water quality of River Yamuna, said the minister.
Being an integrated project, sludge management has also been included in the scope of the work as per which the sludge will be properly disposed of in a scientific manner addressing the environmental-related issues.
Presently in Delhi, under Namami Gange Programme, a total of 11 projects for the treatment of 1268 MLD sewage have been taken up at a cost of Rs. 2009 crore by NMCG to conserve River Yamuna.
The major share of these projects is being borne by the Central Government through the Namami Gange Programme. These projects are targeted to create a total treatment capacity of 1268 MLD in the catchment area of Coronation Pillar (Coronation Pillar STP completed), Kondli, Okhla and Rithala in Delhi.
These projects are targeted to be completed by December 2022.
At the Okhla Sewage Treatment complex, there are six wastewater treatment plants – Phase-I (136 MLD), Phase-II (55 MLD), Phase-III (205 MLD), Phase-IV (168 MLD), Phase-V (73 MLD) and Phase-VI (136 MLD). The existing Phase-I, II, III and IV plants were constructed before 1993.
As the old plants outlived their life, it was decided that a new STP of combined capacity of Phase I, II, III & IV (136+55+205+168) = 564 MLD is constructed with stringent effluent parameters including removal of Biological Nutrients.
It will also have the provision of online monitoring of quality parameters of effluent, SCADA, power generation from biogas and sludge management etc.
Advertisement